Last week (Week 8), the group focused on the machining of the throttle pedal, in addition to ordering the material for the adjustable slides.
This week (week 9), the group manufactured the adjustable slides for the machine shop. Before thye physically manufactured the product, the overall design was updated by a senior member of Formula SAE. This design can be seen below.
A small edge of metal was added to the side of the adjustable slide in order to absorb more force from the pedal box. Additionally, more metal was added beneath the bolts connecting to the chassis in order to add more support to the overall system. A photo of the product (halfway through manufacturing), as well as a video of the manufacturing, can be seen below:
Lauren made spacers for the gap between the pedals and pressed the bearings for the brake pedals. In order to do this, she first had to bore the hole for the brake pedal bearing. A video of machining this week can be seen below:
In addition to machining, the group constructed the pedal box, in order to make sure the design fits together.
Finally, the group worked on their final presentation and their final report, due June 6th.
Next week, (Week 10), the group will completely construct the pedal box. They will present their findings on Wednesday, June 6th.